Etzel III connecting pipeline
Developer
E.ON New Build & Technology GmbH, Gelsenkirchen

Download the project description
PDF, 996 KByte
|
Project
- Connection of the Etzel III gas accumulator plant to the NETRA and BEP long-distance gas pipelines
- The DN 600 connection to the BEP pipeline is approx. 900 m long
- The DN 800 connection to the NETRA pipeline is approx. 200 m long and is laid largely parallel to the BEP connection.
- High groundwater levels and moorland in the construction area
Our services
- Soil and subsoil analysis along the route and trench
- Foundation expert report
- Application for water permit
- Gathering evidence for waterways management
|
| |
|
Expansion of storage facility, Bierwang Unterreit
Developer
E.ON Gas Storage GmbH

Download the project description
PDF, 165 KByte
|
Project
- Construction of a new compressor unit including all ancillary facilities
- Widely varying subsoil conditions with organic soils and confined groundwater conditions
- Compressor unit with hall, surface area approx. 17 m x 25 m; with waste gas chimney
- Gas cooler, surface area approx. 17 m x 27 m
- Heating control station, burnable gas building, function building, cogeneration unit
- Construction and fortification of open spaces
Our services
- Subsoil analysis and foundation expert reports
- Opinion on water rights situation
- In-construction checks and specialist technical processing during the construction period
|
| |
|
Rerouting of natural gas pipeline no. 1
Developer
Open Grid Europe GmbH, Essen

Download the project description
PDF, 149 KByte
|
Project
- Renewal of the crossing at km approx. 18.009 as part of upgrade of DB track section Nuremberg-Ebensfeld (VDE 8.1)
- The pipeline has a diameter of DN 300
- It runs alongside the track for approx. 1.27 km
- DB track crossed with HDD
- Water retention measures required due to the high native groundwater in the project area
Our services
- Soil and subsoil analyses
- Hydroengineering surveys
- Calculation of construction water drainage requirements
- Assessment of groundwater conditions
- Subsoil assessment and foundation work consultancy for the rerouting of the pipeline and crossings, inc. trenches
|
| |
|
Rothenstadt – Schwandorf
natural gas pipeline
DN 1.000 / PN 100
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 166 KByte
|
Project
- Construction of an approx. 41 km long natural gas pipeline parallel to an existing E.ON gas pipeline DN 800
- Approx. 900 m single pipeline laid in village of Wildenau
- A total of 21 roads, rivers and railway lines crossed in enclosed form (product and pipe jacketing)
- Net construction costs: 57 million euros
Our services
- Application for water permit
- Gathering evidence for waterways management
- Soil and subsoil investigations
- Preparation of documents for planning approval
- Supervision of civil engineering works (full time)
- Coordination of preliminary and accompanying archaeological examinations
- Coordination of drainage
- Supervision of civil engineering works in accordance with E.ON regulations and landscape management support plan requirements
- Verification of measurements / settlement of civil engineering services
|
| |
|
New connection Essener Norden
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 149 KByte
|
Project
- New connecting pipe DN 200
- Length approx. 2,950 m
- Connects the existing pipes at the former Matthias Stinnes pit (Essen-Karnap) and Wallstraße (Gelsenkirchen-Horst)
- The pipe is laid largely in public traffic areas
Our services
- Soil and subsoil investigations
- Gathering evidence for waterways management
- Route investigation for the new pipeline, including determination of quantities for the civil engineering specifications
- Water surveys
- Construction support
- Chemical analyses and results reports
- Subsoil investigations and expert reports for inliner renovation
|
| |
|
MEGAL loop pipe Schwandorf - Windberg
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 187 KByte
|
Project
- MEGAL loop pipe in the section between Schwandorf (Bavaria, districts of Schwandorf, Cham, Straubing) and Windberg
- Special construction methods (culverts, HDD where appropriate, microtunnels) required for crossing the Naab and Regen rivers
Our services
- Route investigation for the new pipe
- Soil and subsoil reports
- Determination of quantities for the civil engineering specifications with measurements of the drainage flows, slope stabilization etc.
- Special expert reports for road and rail crossings and for new station structures (pigging and valve stations and gas pressure measuring and control installations) and for the special Naab and Regen crossings
- Gathering water engineering evidence (drainage planning)
|
| |
|
Embedding of spherical sleeve pipes and gas pipelines
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 93 KByte
|
Project
- Replacement of spherical sleeve pipes DN 600 due to stress anomalies
- Various sections between Salzgitter and Helmstedt
Our services
- Subsoil analyses
- Soil reports with subsidence forecasts
- Geotechnical expert reports
- Interpretation of geological maps
|
| |
|
Field pipe to cluster point S 83-86
Developer
Kommunale Gasspeicher-gesellschaft EPE mbH & Co. KG through E.ON Engineering GmbH, Gelsenkirchen

Download the project description
PDF, 163 KByte
|
Project
- Construction of a new approx. 3.8 km long natural gas field pipe for the connection of cluster points
- HDD crossing
- Cavern sites
Our services
- Subsoil analysis and foundation expert reports
- Study of the feasibility of the HDD in a nature conservation area
- Hydroengineering surveys
- Gathering evidence to meet water legislation requirements
- Preparation of the applications required under water legislation for the withdrawal and introduction of groundwater and water for hydraulic pressure tests
|
| |
|
Connecting pipes to the gas transfer station of Shell Deutschland Oil GmbH, Wesseling
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 190 KByte
|
Project
- Connection of 2 approx. 60 m gas connecting pipes
- The transfer station is in a flood-protected area in the hinterland of the main Rhine dike
- The pipes to be connected are on the Rhine floodplain
Our services
- Investigation programme
- Soil and subsoil investigations
- Gathering evidence for waterways management
- Approval under water and dike legislation
|
| |
|
Ethane pipe DN 600, Dornum -Wilhelmshaven
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 135 KByte
|
Project
- Construction of an ethane pipe DN 600 between Dornum and Wilhelmshaven, eastern Friesland
- Total length of the construction section examined: 50.1 km
- Various waterway crossings
Our services
- Subsoil analyses
- Soil mechanical laboratory tests
- Subsoil expert reports and foundation recommendations
- Contaminated site examinations
- Gathering evidence for hydroengineering
- Drainage planning
- Preparation of applications for permits under water and nature conservation legislation
|
| |
|
Gas pipeline no. 083,
Lauterbach – Scheidt (LBS)
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 183 KByte
|
Project
- Construction of a new 124 km natural gas pipeline between the Scheidt station in the Westerwald and a new station in Lauterbach in the Vogelsberg
- Approx. 330 crossings in total
- Diameter DN 1,000
Our services
- Application for water legislation permits / supplementary soil analyses
- Gathering evidence for waterways management
- Soil and subsoil investigations
- Preparation of documents for planning approval
- Expert opinions
- Consulting support for construction
|
| |
|
Connecting natural gas pipeline Luxembourg / DN 500
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 153 KByte
|
Project
- Construction of an approx. 107 km natural gas pipeline DN 500 to connect Remich (Luxembourg) with the Mittelbrunn compressor station (Rhineland-Palatinate)
- Crossing several motorways, track systems and the major rivers of the Saar (at Merzig) and Mosel (at Remich)
Our services
- Hydrogeological expert reports
- Application for water permit
- Gathering evidence for waterways management
- Soil and subsoil investigations
- Preparation of documents for planning approval
- Special expert reports for passing under the Mosel and Saar by means of Horizontal Directional Drilling (HDD)
- Coordination of drainage
- Supervision of civil engineering works in accordance with E.ON regulations, landscape management support planning and waterways management requirements
- Verification of measurements / settlement of civil engineering services inc. drainage measures
|
| |
|
113. Diversion of South
Westphalia pipeline, Dortmund
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 276 KByte
|
Project
- Works site with former intensive industrial use
- The pipeline, DN 700, DP 16, is approx. 300 m in length
- The key aspect of the pipeline diversion is a pressing approx. 80 m in length beneath extensive track works
Our services
- Investigation concept
- Soil and subsoil investigation
- Field tests and lab tests
- Assessment of subsoil and advice on foundations
- Gathering of evidence in relation to water management
|
| |
|
Shell-Pipeline Connect IGO
Developer
Shell Deutschland GmbH, Köln

Download the project description
PDF, 198 KByte
|
Project
- Pipeline connection between the two Shell refineries, part works Nord Godorf and part works Süd Wesseling
- Both part works are on the left bank of the Rhine
- Pipeline link approx 3.9 km, DN 2,000
- Two x Rhine crossings using HDD (horizontal direction drilling). On the right bank of the Rhine, the two HDD pipes are connected via an onshore pipe.
Our services
- Soil and subsoil investigation
- Lab and field investigations, on the land and in the Rhine
- Monitoring of construction
- Geophysical investigation
- Assessment of subsoil and advice on foundations
|
| |
|
Expansions to stations at
Schwarzach and Hügelheim
Developer
TENP GmbH & Co.KG, Essen

Download the project description
PDF, 116 KByte
|
Project
- Expanding the compressor stations at Schwarzach, near Rheinmünster, and Hügelheimm near Mülheim
- New construction of compressors and ancillary units
- Hall with floor area approx. 22.8 x 15.8 m
- Oil cooler with floor area approx. 8.7 x 2.8 m
- Exhaust gas chimney with dimensions approx. 7.2 x 6.8 x 32 m, erected on reinforced concrete foundations with embedded anchor cage
Our services
- Investigation concept
- Soil and subsoil investigation
- Field tests and lab tests
- Gathering of evidence with regard to water laws
- Assessment of subsoil and advice on foundations
- Support during construction and checks on compression
|
| |
|
Etzel natural gas store, station expansion
Developer
E.ON Engineering GmbH, Gelsenkirchen

Download the project description
PDF, 111 KByte
|
Project
- Expanding storage capacity of the natural gas store
- Building a new compressor hall
- Expanding and converting ancillary facilities and station pipework
- Cavern spaces
- High groundwater levels and moor soils in the construction area
Our services
- Investigation of subsoil and report on foundations
- Opinion in respect of water laws
|
| |
|
Natural gas transport pipeline, Forchheim – EKW Irsching
Developer
E.ON Ruhrgas AG, Essen

Download the project description
PDF, 147 KByte
|
Project
- New construction of 12 km natural gas pipeline, DN 800
- Danube crossing via 500 m microtunnel
- Crossing hydrogeologically sensitive areas
Our services
- Applying for permission under water laws
- Gathering of evidence in relation to water management
- Soil and subsoil investigations
- Preparing documents for defining plans
- Monitoring of construction for the underground engineering measures (full time)
- Coordinating archaeological investigations before works and during construction works
- Coordination of water raising
- Monitoring underground civil engineering in accordance with E.ON regulations and accompanying landscape conservation plan conditions
- Examination of overmeasures / Accounts for underground civil engineering
- Conducting discussions to reach agreement with third-party pipeline operators and neighbours affected (routing law)
|
| |
|
District gas pipeline,
Lichtenbusch-Stolberg
Developer
E.ON Ruhrgas AG, Essen
Download the project description
PDF, 151 KByte
|
Project
- New construction of 12 km natural gas pipeline, DN 800
- Outlying urban area with constraints for building
- Crossing a DB tunnel
- Crossing areas subject to previous contamination
- Pipework pressings up to 110 m
Our services
- Applying for permission under water laws
- Gathering of evidence in relation to water management
- Soil and subsoil investigations
- Preparing documents for defining plans
- Monitoring of construction for the underground engineering measures (full time)
- Coordinating archaeological investigations before works and during construction works
- Coordination of water raising
- Monitoring underground civil engineering in accordance with E.ON regulations and LBP conditions
- Examination of overmeasures / Accounts for underground civil engineering
- Conducting discussions to reach agreement with third-party pipeline operators and neighbours affected (routing law)
|
| |
|
IGO 50 ppm pipeline project
Developer
Shell Deutschland GmbH, Köln
Download the project description
PDF, 133 KByte
|
Project
- New construction of a pipline link 5377 m in length between Shell Rhineland refineries at the Godorf and Wesseling plants
- 4 x DN 300 pipelines
- 2 culvert constructions for the Rhine in Lülsdorf and Langen
- Crossing transport routes and Rhine culverts
Our services
- Geotechnical and geophysical investigations
- Core drillings and samples extracted by driving
- Geo-electrical and seismic reflected signal investigation
- Soil mechanics lab tests
- Reaching agreement with countryside protection agencies, Cologne water proection agency and local authorities
- Investigation of pipeline route
- Investigation of subsoil and advice on foundations
|
| |
|
"ARD" natural gas pipeline,
Achim-Rehden-Drohne, Ltg. 088
Developer
E.ON Ruhrgas AG, Essen
Download the project description
PDF, 119 KByte
|
Project
- Construction of a natural gas long-distance pipeline, DN1100 / DP100 between Achim and Drohne, North Germany
- Overall length 91.6 km
- Crossing waterways and road, including a motorway, the Weser, and 5 railway sections
Our services
- Investigations of subsoil
- Soil mechanics lab tests
- Report on subsoil and recommendation regarding foundations
- Investigations for areas subject to earlier pollution
- •Gathering of evidence in relation to hydraulic engineering
- Drainage plans
- Drawing up application documents for permissions under water laws and nature protection laws
|
| |
|
Natural gas long-distance
pipeline, Schmölln-Lubmin (FGL 305)
Developer
Pipeline Engineering Consulting GmbH , Berlin
Download the project description
PDF, 132 KByte |
Project
- Construction of a natural gas long-distance pipeline, DN 1200, between the planned FGL 304 (to the north-west of Schmölln) and the site of the power plant at Energiewerke Nord, Lubmin
- Overall length of the section for construction under investigation 115 km
Our services
- Investigations of subsoil
- Soil mechanics lab tests
- Report on subsoil and recommendation regarding foundations
- Investigations for areas subject to earlier pollution
- Gathering of evidence in relation to hydraulic engineering
- Drainage plans
- Drawing up application documents for permissions under water laws and nature protection laws
|