Suspicion of old mine workings on the Dortmund HBF - Witten track
Developer
DB Netz AG, Hagen
Download the project description
PDF, 842 KByte
|
Project
- DB section 2801 is a two-track section.
- Following a 2004 report on the mining and geotechnical situation and with regard to stability of the surface, there is a high likelihood that the section of track between km 24.000 and km 24.770 is susceptible in places to risks of sinkholes, subsidence and settling
Our services
- Establishment of basis of the project
- Investigative and stabilization concept
- Invitation to tender
- Expert support for the investigative and stabilization measures
- Final documentation
|
|
|
Former Happurg / Doggerstollen tunnel system in the Houbirg
Developer
State Office for Construction, Nuremberg, civil engineering department
Download the project description
PDF, 874 KByte
|
Project
- In accordance with legislation on dealing with the after-effects of war, areas in the Doggerstollen tunnel system in the Houbirg at Happurg that are at risk of collapse will be permanently stabilized
Our services
- General establishment of basis of the project
- Performance of project and structural engineering planning pursuant to HOAI § 43 and HOAI § 49 for stages 1 - 2
- Examination of options and agreement of the project goals with the general public parameters in the form of a decision paper for construction (ES-Bau)
- Landscape management support plan
- Special species protection assessment
- FFH impact assessment
|
|
|
Stabilization measures in Herzkamper basin, Sprockhövel
Developer
RWE Service GmbH, Essen
Download the project description
PDF, 936 KByte
|
Project
- The shallow mine of the "Hauptflöz" layer in the vicinity of the properties at Zum Sportplatz 10-14 in Sprockhövel was investigated and stabilized on behalf of Alte Haase Bergwerks-Verwaltungs-Gesellschaft mbH, Dortmund
- According to official figures the mine extends over a distance of approx. 160 m
- It is located in the vicinity of a school, a kindergarten and below the "Zum Sportplatz" road.
Our services
- Planning and invitation to tender for the investigative and stabilization measures
- Expert support for the investigative and stabilization measures
|
|
|
Expert report on mine damage
at Winterberg-Silbach
Developer
DB Netz AG, West Region, Bergisch-Märkisches Land, Bestwig
Download the project description
PDF, 966 KByte
|
Project
- Expert report on the rock cutting of DB track section 2854, km 19.864 in the vicinity of the village of Winterberg following the appearance of a sinkhole over a former mine gallery
Our services
- Clarification of the cause of the damage
- Inspection of mine plans and elevations
- Study of the stabilization options
- Technical support
|
|
|
Visitor gallery in the former "Neu Glück" pit
Developer
Town of Plettenberg
Download the project description
PDF, 785 KByte
|
Project
- Restoration of the "Neu Glück" pit
- The town of Plettenberg has been using the galleries of the former "Neu Glück" pit on Weidenstraße for guided tours since 2008
- The galleries show localised fissures, giving rise to fears of significant detachment
Our services
- Geotechnical survey
- Stability investigations
- Proposals for stabilization
- Pit visits
|
|
|
Stability of rock-cut cellars in Überlingen
Developer
Town of Überlingen am Bodensee, Urban Development & Greenery
Download the project description
PDF, 309 KByte
|
Project
- Hollows have been dug in the rock walls in the municipal gardens and in the adjacent Grundgraben in Überlingen for a variety of purposes since the Middle Ages.
- The gardens contain what is known as the Kneipp cellar.
- Size approx. 8 m x 3 m, up to approx. 3 m high
- The Grundgraben contains the rock-cut cellar used by the town gardeners as a store, approx. 50 m long, up to approx. 8 m high and with a span of approx. 6 m
Our services
- Geotechnical analyses of stability
- Consulting services
- Study of various stabilization options
|
|
|
Investigative and stabilization measures for 3 surface shaft openings in Mülheim
Developer
Arnsberg District Authority, section 63 – old mines
Download the project description
PDF, 320 KByte
|
Project
- 3 former mineshafts in Mühlheim are being examined with regard to risk management for Arnsberg District Authority
Our services
- Expert support for the investigative and stabilization measures
- Analysis of the mine plans and elevations and the mining documents Preparation of the analys
- Preparation of tender documents
|
|
|
Cracks and damage on a residential building in Minden
Developer
Arnsberg District Authority, section 63 – old mines, Dortmund
Download the project description
PDF, 286 KByte
|
Project
- Cracks and damage on a 1.5-storey residential building on a hillside in Minden
- The cracks might be caused by near-surface coal mining
Our services
- Inspection of mine plans and elevations
- Preparation of an investigation concept
- Preparation of tender documents
- Expert support for the investigative and stabilization measures
- Final documentation
|
|
|
Sinkhole on Zechenstraße, Dortmund
Developer
RWE Services GmbH, Dortmund
Download the project description
PDF, 350 KByte
|
Project
- A sinkhole has appeared on Zechenstraße in Dortmund, near a former air raid shelter
Our services
- Subsoil investigations through soundings
- Preparation of a more detailed investigation concept
- Preparation of the tender documents for the investigative and stabilization measures
- Technical site management of the mining investigations and the backfilling and compaction works
- Final report
|
|
|
Sinkhole in a vineyard
Developer
Freiburg im Breisgau Administrative Court
Download the project description
PDF, 302 KByte
|
Project
- Sinkhole in a vineyard on the edge of the Rhine rift valley as a result of an old iron ore mine
- Diameter approx. 25 m, depth also approx. 25 m
Our services
- Inspection of mine plans and elevations
- Inspection of mine
- Assessment of stability
- Expert report for the court
|
|
|
Construction of new commercial premises above a former hard coal mine, Witten
Developer
E.ON Montan GmbH, Gelsenkirchen
Download the project description
PDF, 705 KByte
|
Project
- Construction of a new supermarket on the premises of a former car workshop
- On the grounds is an abandoned surface shaft opening (Crone shaft: diameter ≈ 2.8 m, depth ≈ 44 m), that is neither filled in nor secured
Our services
- Subsoil assessment
- Subsoil evaluation and foundation work consultancy
- Risk assessment
- Inspection of mine plans and elevations
- Investigation of mine condition
- Safety coordination
- Expert support for the filling/compaction works on mine cavities (former Crone shaft)
|
|
|
Shaft investigation and renovation, Clarenberg lunettes, Dortmund
Developer
RWE Service GmbH, Essen
Download the project description
PDF, 1056 KByte
|
Project
- Investigation and inspection of two former lunettes in Dortmund-Hörde
- According to official figures the shafts have a vertical depth of approx. 18 m and 20 m
Our services
- Inspection of mine plans and elevations
- Preparation of the investigation concept
- Preparation of tender documents
- Supervision of works
- Specialist support
- Evaluation of the stability of the shafts
|
|
|
Stabilization of Girondelle 3 and 4 stratum, Clarenberg, Dortmund
Developer
Arnsberg District Authority
Download the project description
PDF, 1005 KByte
|
Project
- Danger of a cave to the surface caused by workings of a vein
- Downfall zones were discovered in several offset holes drilled under Benninghofer Straße
Our services
- Access holes in the area of Benninghofer Straße
- Construction support for access and fill holes
- Specialist support
- Supervision of works
|
|
|
Construction of new health centre in Witten-Annen
Developer
PBC Bauconsult GmbH,
Castrop-Rauxel
Download the project description
PDF, 196 KByte
|
Project
- Partially cellared, mainly 5-storey business premises with penthouse
- Footprint approx. 70 m x 33 m
- Reinforced concrete structure with supporting brickwork
Our services
- Soil classification, geostatic calculations
- Subsoil investigation, foundation works consultancy
- Inspection of mine plans and elevations
- Mine inspection because the land is located within the Lower Rhine-Westphalia hard coal and ore mining region
|
|
|
Mine stabilization of
Friedrich shaft, Witten
Developer
Alte Haase Bergwerks-Verwaltungs-Gesellschaft mbH
Download the project description
PDF, 160 KByte
|
Project
- Investigation of the sloping Friedrich shaft
- Depth 61 m
- The shaft was immediately adjacent to a public road
Our services
- Preparation of the investigation concept
- Supervision of works / expert support
- Evaluation of exploratory/investigative works
- Concluding report and documentation
|
|
|
Residential property at
Nußbaumweg 10,
Witten-Bommern
Developer
Mr Hobeling, Witten
Download the project description
PDF, 229 KByte
|
Project
- New construction of 2-storey, full-basement residential property with a footprint of approx. 150 m²
- The property is situated close to the former mining site of the Witten coal mine (Geitling hard coal stratum)
Our services
- Investigation and assessment of the subsoil in accordance with DIN 4020
- Recommendations on foundations
- Geothermal report
- Assessment of drainage capacity
- Inspection of plans and elevations for mines
- Tender for investigation of mines and expert support and evaluation of the results from drillings
- Planning and tendering for in-filling of the former mine
- Support during construction
|
|
|
New construction of a
residential
facility, Project
Stockumer Straße, Bochum
Developer
Kriener Wohnungsbau-gesellschaft mbH, Witten
Download the project description
PDF, 105 KByte
|
Project
- Constructing a residential facility with 16 semi-detached units on a former industrial site
- Total area 5,700 m²
- Measures for redevelopment of a former mining area
- Restoration of the subsoil
Our services
- Concept for demolitions works, reinstatement concept including on-site support during construction
- Investigation and assessment of the subsoil in accordance with DIN 4020
- Recommendations regarding foundations
- Investigation of inherited pollution
- Inspection of plans and elevations for mines at the Arnsberg district authorities
- Expert examination and report on in-filling of mining works
|
|
|
New construction of a hotel complex, Selmastraße, Essen
Developer
KapHag Architektur und Bau GmbH, Berlin
Download the project description
PDF, 139 KByte
|
Project
- Hotel complex with 7 upper storeys in Essen City, covering an area of 4,000 m²
- Previous development was destroyed during WW2
Our services
- Examination of the subsoil
- Report on foundations for the new building, taking account of influences from mining
- Initial assessment of inherited pollution
- Inspection of plans and elevations for mines, risk assessment
- Support for investigative, infilling and compaction drilling to secure the empty chambers left over from mining
|
|
|
New construction of a residential facility,
Dachsweg, Dortmund
Developer
Kaefer GmbH, Bremerhaven
Download the project description
PDF, 112 KByte
|
Project
- New construction of a 3 ½ storey semi-detached house on a sloping site
- Site over a former mining works
Our services
- Inspection of plans and elevations for mines
- Risk assessment
- Tendering for investigative measures
- Expert monitoring of investigative drillings for shafts and mining chambers
- Assessment of the current safety of the site
- Expert monitoring of infilling and compaction works to fully secure the site
|
|
|
New construction of a dental-biomedical R&D centre( ZBZ) ,
Karl-Herrhausen-Str., Witten
Developer
ZBZ - Witten GmbH
Download the project description
PDF, 161 KByte
|
Project
- New construction of a dental-biomedical R&D centre (ZBZ)
- 5-storey building comprising 4 round towers
- Given the sloping site, the cellar level was below the site surface level on the side to the road
Our services
- Assessment of subsoil
- Advice regarding foundations
- Percolation report
- Taking account of influences from mining
|
|
|
New construction of residential housing, Project Strontianitstraße, Ahlen-Vorhelm
Developer
Bendix, Ahlen
Download the project description
PDF, 111 KByte
|
Project
- Planned development on an area covering 12,000m² in Ahlen-Vorhelm
- Site above a former vertical face for mining of strontianite
- Shown as an area at risk from mining in the spatial use plan
Our services
- Inspection of plans and elevations for mines
- Risk assessment
- Tendering for investigative measures
- Geotechnical recording of excavator prospecting works to determine the site of the course of strontianite
- Expert monitoring of investigative drillings for a shaft and mining chambers
- Assessment of the current safety of the site
|
|
|
Prometheus, Ruhr-Universität
Bochum
Developer
rubitec GmbH, Bochum

Download the project description
PDF, 143 KByte
|
Project
- Sinking two drill holes to a depth of 4,000 m
- Obtaining geothermal energy on the site of FH Bochum
- Size of drilling site 7,500 m²
- At a depth of around 1,000 m there are production caverns established in former mining chambers.
Our services
- Investigation of the subsoil, assessment of subsoil and advice on foundations for the drilling site
- Inspection of plans and elevations for mines
- Inspection of the archive of air protection facilities
- Risk assessment
|
TOP |
|